Liquor Modernization Project

FIRST AGENCY TO GO LIVE

19 Apr 2017

FIRST PHASE 2 DELIVERY

1 May 2017

LAST 1.5 DELIVERY

9 Jun 2017

Summary Info

172294 Cases
41

Groveport DC

Capacity: 425000 Cases

14171 Cases
4

Green DC

Capacity: 450000 Cases

20 Agencies
5

Agencies Live

Total: 465 Agencies

446 Installed
96

Wireless Installs

Total: 465

378 Agencies
82

Scanners Shipped

Total: 465

The Liquor Modernization Project (LMP) will bring up to date the long-outdated processes used in Ohio's liquor business. Current business processes are more than 40 years old, and need to be modernized to meet today's business challenges and to prepare for future growth.

Continuing to use these outdated processes is like listening to your favorite songs on an 8-track tape when everyone else is streaming music on their smartphones.